A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows:

+1 vote
16 views
asked Mar 14, 2018 in Mathematics by paayal (26,720 points) 4 6 11

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

1 Answer

0 votes
answered Mar 14, 2018 by sanjaydas (61,430 points) 5 7 7
selected Mar 15, 2018 by faiz
 
Best answer

Solution: a = 200 , d = 50 and n = 30

S30 = 30/2(400+50 x 29) =27750

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

One Thought Forever

“There is a close connection between getting up in the world and getting up in the morning.“
– Anon
~~~*****~~~

...